Still on the first dump, and the second ready to drop. |
The objective today was to put in the 4th layer. Unfortunately, for a number of reasons we did not manage this, and just got 45 meters in. Still, looking back over the week, we reckon we transported and levelled 200 tons of infill, with 3 1/2 layers done, and 1 1/2 layers still to go. The platform has been transformed!
Here is the main reason we did not fill as much as we had hoped today:
The big sky - unfortunately, also the small pile. |
No infill available ! We are rather dependent on our kind suppliers Kier, and today some of the crushed concrete they had was used under their piling rigs, so that up to a point we had to make do with what was left over from yesterday.
No, not crisps, water. |
Thirsty work for a CAT. |
Tony and Ron have a chin wag. |
As the spoil shortage had also impacted Kier's activities, the ordered some crushed stone from a quarry, and very kindly rerouted one of these lorries over to us. Now that is friendly! We were off again, but now in yellow. It looked rather odd, but that's the Cotswolds for you.
4270 comes to inspect our work |
Friday is a non-running day, so we are not slowed down by passing trains. Not!
Peculiar arm waving by the shovel gang as I mounted the platform infill caused me to slow down and stop. It was 4270, let out for a canter. Nice. I am so impressed by this locomotive, being a shareholder of 4253, which still has some way to go, but this is what we will get. Fabulous.
What's this yellow stuff you're bringing us then? |
The crushed Cotswold stone was very sticky and almost impossible to shift, even with pick and shovel. Eventually we cracked, and ordered a 1 1/2 ton mini digger to help distribute the material. It arrived within the hour - now that is service.
Rolling, rolling, rolling..... |
Finally, the 45m we filled were rolled by John, leaving a nice packed surface.
This is the end of our working CRC2 week, and tomorrow were are having a 'holiday' at Broadway. the signal box is calling us...
We will be back at CRC2 on Monday to progress the fourth layer - other days are not yet certain.
3 comments:
Thanks for the updates, Jo, they are read and appreciated. I'm involved the frustratingly slow extension of the line at Llangollen, so I take a particular interest in other challenges!
Awesome work, as ever, chaps! Spot on comments regarding 4270 and 4253, which is coming on really well at the KESR considering the years it spent at ~Barry and then in the "Rippingale Scrapyard" at Blaenavon. As a shareholder in 4247 (now sadly too far away for me at Bodmin) I think these 2-8-0Ts are just great for heritage lines like ours. Of course, before preservation, they were quite rare east of Gloucester.
Looking for what 4253 might sound like, I came across this clip of 4247 going up Tenterden bank:
http://youtu.be/9uLoGRic8mc
I think you got value for money there, as a shareholder, Ted :-)
Post a Comment